Specification Development Cycle
HTNG certification for Web Service-based interface specifications operates on a twice-annual cycle. The following due dates have been established for upcoming releases. These dates do not apply to non Web Service-based specifications.
Workgroup leaders and participants should pay careful attention to the dates and deliverables outlined below, as time extensions are generally not possible. Any questions may be directed to the HTNG workgroups mailbox.
- Each workgroup must have a board-approved charter and project plan in place before beginning the specification development process.
- Each deliverable must be posted to the collaboration site by 11:59pm EDT/EST on the due date listed. The deliverables must minimally meet the requirements designated by HTNG and will be reviewed by HTNG staff for completeness.
- After all deadlines are met and the HTNG staff has finished formatting, the documentation will be released to the HTNG community for a two-week review period during which any and all concerns should be raised. If major revisions are proposed during this period, one possible outcome is that final release will not occur during the current release cycle.
- Once the review period closes, the workgroup will have time to make any final (minor) changes. The documentation will then proceed to a ratification vote by voting members of the workgroup. Votes will be open for a minimum of seven (7) days.
- In the event of extensive changes or at HTNG's discretion, general release may be delayed to allow time for final cleanup and formatting.
Due Dates for the 2013B Specification Development Cycle
| Deliverable | 2013B Due Date |
|---|---|
| High-Level Role Identification | 03 May 2013 |
| Initial Use Case Listing | 10 May 2013 |
| Completed (Filled) Use Cases |
07 Jun 2013 |
| Data Element Identification | 05 Jul 2013 |
| Preliminary Schemas and WSDLs | 26 Jul 2013 |
| Sample Messages | 16 Aug 2013 |
| Messaging Matrix | 23 Aug 2013 |
| Final Role Identification | 23 Aug 2013 |
| Completed Data Element Tables | 30 Aug 2013 |
| Message Flow (UML) Diagrams | 30 Aug 2013 |
| Technical Specification | 06 Sep 2013 |
| Conformance Statement Questionnaire (CSQ) |
13 Sep 2013 |
| Product Specification | 13 Sep 2013 |
| Document Formatting by HTNG Staff |
20 Sep 2013 |
| Final Schemas and WSDLs | 20 Sep 2013 |
| Start of Review Period / Released for Member Comment |
20 Sep 2013 |
| Close of Review Period | 05 Oct 2013 |
| Vote Begins on All Documentation | 12 Oct 2013 |
| Vote Closes | 19 Oct 2013 |
| 2013B General Release | 19 Oct 2013 |
| Available for Certification | 16 Nov 2013 |
Due Dates for the 2014A Specification Development Cycle
| Deliverable | 2014A Due Date |
|---|---|
| High-Level Role Identification | 01 Nov 2013 |
| Initial Use Case Listing | 08 Nov 2013 |
| Completed (Filled) Use Cases |
06 Dec 2013 |
| Data Element Identification | 03 Jan 2014 |
| Preliminary Schemas and WSDLs | 24 Jan 2014 |
| Sample Messages | 14 Feb 2014 |
| Messaging Matrix | 21 Feb 2014 |
| Final Role Identification | 21 Feb 2014 |
| Completed Data Element Tables | 28 Feb 2014 |
| Message Flow (UML) Diagrams | 28 Feb 2014 |
| Technical Specification | 07 Mar 2014 |
| Conformance Statement Questionnaire (CSQ) |
14 Mar 2014 |
| Product Specification | 14 Mar 2014 |
| Document Formatting by HTNG Staff |
21 Mar 2014 |
| Final Schemas and WSDLs | 21 Mar 2014 |
| Start of Review Period / Released for Member Comment |
21 Mar 2014 |
| Close of Review Period | 04 Apr 2014 |
| Vote Begins on All Documentation | 11 Apr 2014 |
| Vote Closes | 18 Apr 2014 |
| 2014A General Release | 18 Apr 2014 |
| Available for Certification | 16 May 2014 |