Specification Development Cycle
HTNG certification for Web Service-based interface specifications operates on a twice-annual cycle. The following due dates have been established for upcoming releases. These dates do not apply to non Web Service-based specifications.
Workgroup leaders and participants should pay careful attention to the dates and deliverables outlined below, as time extensions are generally not possible. Any questions may be directed to the HTNG workgroups mailbox.
- Each workgroup must have a board-approved charter and project plan in place before beginning the specification development process.
- Each deliverable must be posted to the collaboration site by 11:59pm EDT/EST on the due date listed. The deliverables must minimally meet the requirements designated by HTNG and will be reviewed by HTNG staff for completeness.
- After all deadlines are met and the HTNG staff has finished formatting, the documentation will be released to the HTNG community for a two-week review period during which any and all concerns should be raised. If major revisions are proposed during this period, one possible outcome is that final release will not occur during the current release cycle.
- Once the review period closes, the workgroup will have time to make any final (minor) changes. The documentation will then proceed to a ratification vote by voting members of the workgroup. Votes will be open for a minimum of seven (7) days.
- In the event of extensive changes or at HTNG's discretion, general release may be delayed to allow time for final cleanup and formatting.
Due Dates for the 2012A Specification Development Cycle
| Deliverable | 2012A Due Date |
|---|---|
| Definition of Deliverables and Role Identification | 04 November 2011 |
| Initial Use Case and Business Requirements Listing | 11 November 2011 |
| Completed (Filled) Use Cases and Business Requirements | 09 December 2011 |
| Message Flows (UML Diagrams) | 16 December 2011 |
| Data Element Identification | 06 January 2012 |
| Preliminary Schemas and WSDLs | 03 February 2012 |
| Technical Specification | 24 February 2012 |
| Conformance Statement Questionnaire (CSQ) and Product Specification | 09 March 2012 |
| Completion of document formatting by HTNG staff and completion of Final Schemas and WSDLs | 23 March 2012 |
| Start of Review Period / Released for Member Comment | 13 April 2012 |
| Close of Review Period | 27 April 2012 |
| Vote Begins on All Documentation | 4 May 2012 |
| Vote Closes | 11 May 2012 |
| 2012A General Release | 11 May 2012 |
| Available for Certification | 8 June 2012 |
Due Dates for the 2012B Specification Development Cycle
| Deliverable | 2012B Due Date |
|---|---|
| Definition of Deliverables and Role Identification | 04 May 2012 |
| Initial Use Case and Business Requirements Listing | 11 May 2012 |
| Completed (Filled) Use Cases and Business Requirements | 08 June 2012 |
| Message Flows (UML Diagrams) | 15 June 2012 |
| Data Element Identification | 06 July 2012 |
| Preliminary Schemas and WSDLs | 03 August 2012 |
| Technical Specification | 24 August 2012 |
| Conformance Statement Questionnaire (CSQ) and Product Specification | 07 September 2012 |
| Completion of document formatting by HTNG staff and completion of Final Schemas and WSDLs | 21 September 2012 |
| Start of Review Period / Released for Member Comment | 21 September 2012 |
| Close of Review Period | 05 October 2012 |
| Vote Begins on All Documentation | 12 October 2012 |
| Vote Closes | 19 October 2012 |
| 2012B General Release | 19 October 2012 |
| Available for Certification | 16 November 2012 |
Due Dates for the 2013A Specification Development Cycle
| Deliverable | 2013A Due Date |
|---|---|
| Definition of Deliverables and Role Identification | 02 November 2012 |
| Initial Use Case and Business Requirements Listing | 9 November 2012 |
| Completed (Filled) Use Cases and Business Requirements | 7 December 2012 |
| Message Flows (UML Diagrams) | 14 December 2012 |
| Data Element Identification | 04 January 2013 |
| Preliminary Schemas and WSDLs | 01 February 2013 |
| Technical Specification | 22 February 2013 |
| Conformance Statement Questionnaire (CSQ) and Product Specification | 08 March 2013 |
| Completion of document formatting by HTNG staff and completion of Final Schemas and WSDLs | 22 March 2013 |
| Start of Review Period / Released for Member Comment | 22 March 2013 |
| Close of Review Period | 05 April 2013 |
| Vote Begins on All Documentation | 12 April 2013 |
| Vote Closes | 19 April 2013 |
| 2012A General Release | 19 April 2013 |
| Available for Certification | 17 May 2013 |